| Installing the rebar grid for the concrete sides and bottom. |
| Checking the rebar measurements for the lid. |
| Putting on the finishing coat of smooth concrete. The cistern will rest and dry for a couple of months before painting with sealant. |
| Installing the rebar grid for the concrete sides and bottom. |
| Checking the rebar measurements for the lid. |
| Putting on the finishing coat of smooth concrete. The cistern will rest and dry for a couple of months before painting with sealant. |
| The top and right sides are almost complete, only lacking the sheet metal along the outside of the fence. |
| The bottom-side posts are in place. Here, Yano is mixing cement. You can see the rocks they are putting under the fence for "digging protection." |
| Alan (14), Antony (10), and Alex (13) |
| They dug the holes with pickaxes and shovels using a plumb line to go straight down. |
| They hauled the dirt out by bucketfuls. The guys worked in a team of 3: one digging, one pulling up the buckets, and one carting away the dirt in a wheelbarrow. They traded positions every hour. |
| It took two weeks to finish, and the final holes were 12 and 15 meters deep, respectively, with concrete around the top two meters. |
| For now, the holes are covered by tin roofing pieces and gnarly tree stumps. Eventually the area will be covered by concrete, with an outhouse building over the closest hole. |